Home/Services/Custom builds/No. 10A plant engineer walked in with a sketch on grid paper. Four weeks later we bolted his 16-port manifold to the press.
Custom Build · Manifold · Industrial🇦🇪 UAE · Jebel Ali (workshop)CASE NO. 10 · MAY 2026 · BAY 7 / WORKSHOP

A plant engineer walked in with a sketch on grid paper. Four weeks later we bolted his 16-port manifold to the press.

A UAE steel-stamping plant had outgrown an OEM 8-port block. The plant engineer arrived in our Jebel Ali workshop with a hand-drawn circuit, a target pressure of 420 bar, and an opinion about cross-bore failures. We turned the sketch into a CAD model, then a billet of EN24, then a certified part bolted to the press the same day it landed.

FIG. 01 · 16-port EN24 manifold on the hydrotest bench, day 24 — 630 bar held 30 minPHOTO · A. AL SUWAIDI · 2026-05-08
Asset
CMB-16P· custom manifold
Ports
16· ISO 6149
Working pressure
420bar (~6,090 psi)
Build cycle
28days
Material cert
EN 10204 3.1
/01

A press line that had outgrown its block.

The plant engineer walked into our Jebel Ali workshop on a Tuesday with a roll of A3 grid paper under his arm. His employer, a UAE steel-stamping plant feeding the construction trade, had upgraded its largest hydraulic press for a planned product-mix change — heavier blanks, deeper draws, longer cycles. The OEM-supplied 8-port manifold block was the bottleneck. He had drawn the replacement himself, in pencil, port-by-port. He was looking for someone who could turn it into a part.

The plant had been running the press on a stacked-modular manifold sourced when the line was first commissioned. Production had grown around it: an extra unloader valve bolted on with a sub-plate, a sequence-priority circuit improvised at the JIC fittings, three relief valves where two would have done. The sketch in his hand cleaned all of that up — 16 ports, two unloader valves, a clean sequence-priority circuit, all on a single block bolted directly to the press frame. The intent was right. The pressure rating was the catch: 420 bar working, 630 bar hydrotest, and a press that runs a duty cycle harder than most mobile gear.

What the plant engineer brought us

"Make this. 16 ports. 420 bar. Four weeks."

A pencil sketch on A3 grid paper. ISO-style symbols, port positions called out, two unloader valves, sequence-priority circuit on the punch side. Target: replace the OEM 8-port block one bay over without re-routing the press plumbing.

What the job actually required

Engineer it, validate cross-bores, machine, certify.

Convert sketch to ISO 1219 schematic + 3D solid + drill plan; validate every cross-bore intersection in CAD before cutting metal; machine from a single EN24 billet (quenched + tempered); hydrotest at 1.5× MAWP; leak-test every port-to-port path; full cert pack to EN 10204 3.1.

A custom manifold is not a part you order. It is a part you engineer. The sketch told us what the customer wanted the hydraulics to do. The cross-bore plan, the material spec, the hydrotest regime, the cleanliness target — those are choices made by the engineer who signs the drawing. On a press running 420 bar with the operator standing two metres away, those choices are the difference between a part that lasts a decade and one that cracks a billet on first pressurisation.

/02

Sketch to CAD to billet to certified part.

We took the sketch, redrew it as an ISO 1219 hydraulic schematic, modelled the block as a 3D solid in CAD, and laid out the drill plan port-by-port. Every cross-bore intersection — every place two drilled passages meet inside the block — was checked in CAD against a minimum-wall rule of 3× bore diameter for high-pressure service. Three intersections came up tight on the first pass; two were resolved by repositioning a port 6 mm, the third by stepping a passage diameter down from 12 mm to 10 mm. None of them got cut into a billet.

The block was machined from a single billet of EN24 alloy steel to BS 970 grade, quenched and tempered, with a tensile strength ≥ 850 MPa certified per the rolling mill batch. Sixteen ports were drilled and threaded to ISO 6149 metric (a mix of M27, M22 and M14 across the circuit), all cross-bores cut per the verified plan, every internal passage deburred and flushed to ISO 16232 cleanliness. Hydrotest at 630 bar for 30 minutes, then a port-to-port pressure-decay leak test on every path with an acceptance limit of < 0.1 ml/min per joint. Cert pack issued to EN 10204 3.1.

FIG. 02Day 18, machining bay. EN24 billet, 16 of 16 ports drilled and tapped, cross-bores cut per the verified plan. The block goes from here to deburr, then cleanliness, then hydrotest.
Cross-bore validation in CAD is not a nice-to-have. The day you skip it is the day you crack a billet at 600 bar with three weeks of machining time inside it. We caught three tight intersections on this block before the first cut.— Hassan Al Awadi · CAD Draftsman / Cross-Bore Checker · Jebel Ali
/03

Four phases — sketch to bolted-up.

Every custom-manifold build we run goes through the same four phases. The sketch goes in at one end. A certified part bolts to the customer's press at the other. Names don't change; only the durations move with the complexity of the circuit.

PHASE 01

Engineering & validation

Sketch to ISO 1219 schematic. 3D solid model of the block. Port-by-port drill plan. Cross-bore minimum-wall check in CAD before any metal is cut.

Days 0 — 7
PHASE 02

Material & machining

EN24 billet sourced with mill cert. Quenched + tempered to ≥ 850 MPa. Sixteen ports drilled and threaded to ISO 6149. Cross-bores per the validated plan.

Days 8 — 21
PHASE 03

Test & certify

Deburr, flush to ISO 16232 cleanliness. Hydrotest at 630 bar for 30 min. Pressure-decay leak test on every port-to-port path. Cert pack assembled.

Days 22 — 25
PHASE 04

Delivery & bolt-up

Crated and shipped to the plant. Bolted to the press in the same shift it landed. Witnessed pressurisation against the OEM control sequence; cert pack handed over.

Days 26 — 28
/04

The SOP we followed, line by line.

Below is the actual SOP we run for a custom manifold build — abridged. SOP-IND-040 in full runs 38 lines covering sketch intake, CAD generation, cross-bore validation, material verification, machining, deburring, cleanliness coding, hydrotest, leak test, and the cert pack. This is the subset that was ticked off on this job.

SOP-IND-040 · CUSTOM MANIFOLD BUILD · REV 0224 / 24 COMPLETE
Phase 01 · Engineering & validation
Sketch intake & circuit reviewPlant engineer's grid-paper sketch reviewed; intent captured against ISO 1219 schematic standard
F. AL MANSOORI
Review
Convert sketch to ISO 1219 schematic16 ports, 2 unloaders, sequence-priority circuit redrawn to standard symbols
F. AL MANSOORI
CAD
3D solid model of the blockFull block geometry modelled; ports placed for direct bolt-up to existing press frame
H. AL AWADI
CAD
Drill plan & port scheduleEvery passage tagged: diameter, depth, thread, sealing face. 16 ports + 11 cross-bores
H. AL AWADI
Drill plan
Cross-bore minimum-wall validation3× bore-diameter rule checked at every intersection. 3 tight passes flagged + resolved
H. AL AWADI
CAD check
Phase 02 · Material & machining
EN24 billet sourced with mill certBS 970 grade, quenched + tempered. EN 10204 3.1 cert on file before machining starts
Y. AL HASHIMI
Material cert
Tensile + hardness verification≥ 850 MPa tensile, hardness banding to 248 — 302 HB. Sample coupon tested in-house
A. AL SUWAIDI
Tensile rig
Block roughed from billetOuter geometry to drawing, mounting-face flatness to 0.05 mm across 320 mm
O. AL MAKTOUM
CNC mill
Drill 16 ports + 11 cross-boresPer validated plan: M27 × 2, M22 × 6, M14 × 8. ISO 6149 sealing faces
O. AL MAKTOUM
CNC mill
Thread & deburr every portTapped ports gauge-checked; cross-bore intersections deburred with carbide rotary
O. AL MAKTOUM
Tap + burr
Phase 03 · Cleanliness & test
Internal flush + cleanliness codingBlock flushed; particle count to ISO 16232 N100 limit for industrial hydraulic components
A. AL SUWAIDI
Flush rig
Hydrotest @ 1.5× MAWP630 bar held 30 min on every port; gauge witness + chart recorder. Zero bar drop
A. AL SUWAIDI
Hydrotest
Port-to-port leak testPressure-decay on every cross-bore path. Limit < 0.1 ml/min per joint. All 27 paths passed
A. AL SUWAIDI
Decay test
External seal + plug acceptance8 working plugs torqued to spec; 8 spare ports plugged with shop plugs for transit
O. AL MAKTOUM
Torque wr.
Cert pack assembledMaterial 3.1, hydrotest cert, cleanliness cert, ISO schematic, drill plan, port schedule — 38 pp
A. AL SUWAIDI
PDF
Phase 04 · Delivery & bolt-up
Crate, tag, shipBlock crated with desiccant, port plugs verified, transit shock indicator fitted
Y. AL HASHIMI
Logistics
On-site fit to press frameOld OEM block removed, mounting face cleaned, new block bolted up — same shift
O. AL MAKTOUM
On-site
Re-route plant plumbing to new portsPlant engineer's tag list followed; every line re-terminated to ISO 6149 sealing face
O. AL MAKTOUM
Wrench set
Witnessed first-pressurisationPress control system run through OEM sequence; manifold held 420 bar working
F. AL MANSOORI
On-site
Cert pack handover & sign-offCustomer countersign on cert pack; 12-month manufacturer warranty issued
Y. AL HASHIMI
Paper
/05

Material, geometry, pressure — the numbers.

Below is what we specified, what we measured, and what we certified on the finished block. Material, cross-bore validation and the hydrotest are the three load-bearing items on a custom manifold — all three are highlighted, all three passed first time.

BUILD RECORD · CMB-16P · SERIAL CMB-2026-010 · INDUSTRIAL PRESS
ComponentSpecAs-foundAfter rebuildStatus
Block materialEN24 (BS 970), Q+TBillet, mill certEN24, 3.1 cert✓ Verified
Tensile strength≥ 850 MPa892 MPa (coupon)892 MPa✓ Pass
Hardness band248 — 302 HB281 HB (avg n=5)281 HB✓ Pass
Port count16, ISO 614916 / 16 gauged✓ All pass
Port mixM27 / M22 / M142 / 6 / 8✓ Per drawing
Cross-bore intersections11, ≥ 3× bore wall3 flagged tight11 / 11 valid↻ Repositioned in CAD
Mounting-face flatness≤ 0.05 mm / 320 mm0.03 mm✓ Pass
Cleanliness codeISO 16232 N100N100 verified✓ Pass
Hydrotest @ 1.5× MAWP630 bar / 30 min hold630 bar / 30 min, 0 bar drop✓ Pass first time
Port-to-port leak rate< 0.1 ml/min per joint0.00 — 0.04 ml/min✓ All 27 paths
Working pressure rating420 bar (~6,090 psi)420 bar certified✓ Stamped on block
Material certificateEN 10204 3.1Mill cert in hand3.1 issued✓ Filed
/06

Same-day bolt-up, press back in production.

The block landed at the plant on the morning of day 27. By the end of the same shift the old OEM 8-port manifold was off the press, the new 16-port EN24 block was bolted to the frame, the plant's lines had been re-routed to the new port positions, and the press control system had run a witnessed first-pressurisation against its OEM commissioning sequence. The press was back in production on day 28 — on schedule for the customer's product-mix change. Full cert pack handed over: material, hydrotest, cleanliness, ISO schematic, drill plan. 12-month manufacturer warranty on the assembled block.

Result · summary

Sketch to certified 16-port EN24 manifold in 28 days. Bolted to the press the same shift it landed, hydrotested 50% above working pressure, zero leaks across 27 internal paths.

Plant engineer's pencil sketch turned into an ISO 1219 schematic, a 3D model, a validated drill plan, and a billet of EN24 — then certified at 1.5× MAWP and bolted to the press in the same shift it landed at the plant. Full cert pack to EN 10204 3.1, 12-month warranty, press back in production on day 28.

28days
Sketch to bolted-up
27 / 27
Leak-test paths passed
630bar / 30 min
Hydrotest hold
12mo
Warranty on assembled block
/07

Five engineers, one workshop, one block.

Five engineers logged time against this work order, all in our Jebel Ali workshop. The customer dealt with one engagement lead from sketch intake to bolt-up. If you call the workshop and ask about case 10, any of them can pull the file.

  • Fatima Al MansooriDesign Engineer, Jebel Ali. Sketch intake, ISO 1219 schematic conversion, customer engagement, on-site witness of first-pressurisation.
  • Hassan Al AwadiCAD Draftsman / Cross-Bore Checker, Jebel Ali. 3D solid model of the block, drill plan, cross-bore minimum-wall validation. Caught three tight intersections before any metal was cut.
  • Omar Al MaktoumMachinist, Jebel Ali. Billet rough-out, port drilling and threading, deburr. Bolt-up at the customer plant on delivery day.
  • Aisha Al SuwaidiQA / Hydrotest Lead, Jebel Ali. Tensile coupon, ISO 16232 cleanliness, 630 bar hydrotest, port-to-port leak test, cert pack assembly.
  • Yusuf Al HashimiWorkshop Manager, Jebel Ali. Material sourcing, EN 10204 3.1 cert chain, build-cycle scheduling, customer handover and warranty issue.

Case file · INTAKE-2026-04-128 · WO-2026-1184 · Published 2026-05-10 · Updated 2026-05-11

SERVICE INTAKE · OPEN 24×7 · JEBEL ALI

If it leaks, hums, screams, drips, slips or simply refuses to move — we’d like a look at it.

Send us a photo, an SKU or a part on a pallet. We’ll do the rest.

An applications engineer will read your ticket inside one business day — no charge for the conversation, no obligation to use us.