Rigging kit for a new site: what to order when mobilising in the UAE and GCC

A new project needs a rigging loft before the first lift: slings, shackles, hooks, chain blocks, tag lines, and a register to track them. What to order, in what mix, how to size it to your cranes and lifts, and how to set up the store, register and inspection cycle so the kit passes its first third-party examination — with an example starter list for a mid-size building site.

Written by
Ayush Bhatia, Director
Published
Reading
5 min · 4 sections
Share

At a glance

Key takeaways

  1. Size the kit from the lift plan: the heaviest planned lifts, the crane hooks, and the number of crews working at once.
  2. Buy in matched sets — slings, shackles and master links rated for the same loads — so riggers never improvise a connection.
  3. Order a spread of capacities, with more of the light and medium sizes that do most of the daily work.
  4. Set up a rigging loft and a lifting register before the first lift; every item is marked, certified and registered on arrival.
  5. In Abu Dhabi lifting accessories are examined every 6 months by approved third parties; plan the first examination into the programme.

Figures verified · Kit structure is general practice; quantities are an example to adapt to the lift plan. UAE intervals from Abu Dhabi and Dubai lifting guidance read September 2026.

Mobilisation is when a site’s rigging habits are set. If the loft opens with a mixed bag of slings from the last project, unmarked shackles and no register, every lift for the next two years inherits it. If it opens with a matched, certified, registered kit sized to the cranes and the lift plan, riggers have the right gear to hand and the first third-party examination is a formality. This guide sets out what to order and how to organise it.

/01Start from the lift plan.

  • Cranes and hooks: tower and mobile cranes on site, their hook sizes and the heaviest load each will handle.
  • Typical lifts: rebar bundles, formwork, steel members, precast, MEP plant, materials in stillages.
  • Heaviest lifts: these set the top of the range — they may need dedicated rigging, engineered by the lifting engineer.
  • Crews: how many rigging crews work at once, so there is a set per crew plus spares in quarantine and inspection.
  • Fixed lifting: plant rooms, lift shafts and workshops where chain blocks, beam trolleys and clamps will live.

/02The core kit.

Core rigging kit by family — what it is for
FamilyUsed forNotes
Round slings and webbing slingsGeneral lifting, finished surfaces, choker hitchesColour-coded by WLL (EN 1492); protect from sharp edges
Chain slings, 2- and 4-legHighlightedSteel, precast, heavy and hot loadsGrade 80 or 100; master link sized to the crane hook
Wire rope slingsHeavy and long-term rigging, abrasive loadsFerrule-secured or spliced eyes; thimbles where eyes bear on pins
ShacklesJoining slings to lugs, hooks and each otherBolt type for anything left in place; see the shackle buying guide
Hooks, master links, swivelsMaking up and connecting assembliesLatched hooks; matched grades
Chain blocks, lever hoists, beam trolleys, beam clampsPositioning and lifting in plant rooms and shaftsLever hoists for pulling and tensioning
Tag linesControlling load rotation from a safe distanceNon-conductive fibre rope
Lifting points and eye boltsAttaching to equipment and fabricationsUse rated points; see eye bolt types and angled loads

/03An example starter list.

As an example only — for a mid-size building site with two tower cranes, two rigging crews and lifts mostly under 5 t — a starter kit might look like the list below. Your lift plan and lifting engineer set the real quantities and capacities; treat this as a checklist of families, not a standard.

Example starter kit — two tower cranes, two crews, lifts mostly under 5 t (adapt to your lift plan)
ItemExample mix
Round slings1 t, 2 t, 3 t, 5 t in 2–6 m lengths; several of each per crew
Webbing slings2 t and 3 t, 3–4 m, for finished and fragile items
Chain slingsTwo- and four-leg Grade 80, sized for the heaviest routine lifts
ShacklesScrew-pin and bolt-type anchor shackles, 2 t to 8.5 t, with spares
Chain blocks and lever hoists1 t to 3 t chain blocks, 1.5 t lever hoists
Beam clamps and trolleysMatched to plant-room beam flanges
Tag linesOne or two per crew, plus spares
Quarantine stockSpare slings and shackles to cover items out for inspection or rejected

/04The rigging loft and register.

  1. Receive: check each item against the purchase order and its certificate, and read its markings — see shackle markings explained.
  2. Register: give every item a unique ID, record WLL, certificate number and next examination date.
  3. Store: slings hung off the floor, out of sun and away from chemicals; shackles and hooks in labelled bins by size; chain blocks on racks.
  4. Issue and return: issue against the register, inspect on return, quarantine anything damaged.
  5. Examine: book the periodic thorough examination; colour or tag items to show they are in date if your site uses a system — not a legal requirement in itself, but a useful one.

Common questions

How many slings does a construction site need?
Enough sets for each rigging crew to work without borrowing, plus spares for items out for inspection or rejected. Your lift plan sets the capacities.
Should I buy Grade 80 or Grade 100 chain slings?
Grade 100 carries more for the same chain size and weight. Do not mix grades within one assembly; see chain grades explained.
Do rigging items need certificates on arrival?
Yes. Each item should be marked with its WLL and come with the manufacturer’s test certificate, which goes into the lifting register.
Is colour coding of lifting gear required in the UAE?
The Abu Dhabi and Dubai documents we have read do not require it, but many sites use colour or tag systems to show items are in date.
Can you supply a full rigging kit?
Yes. Send the lift plan or a list of families and capacities, and we will quote a matched kit with certificates.

Core rigging kit

IndustryConstructionLifting, rigging and plant supply for contractors.

What next

  1. 01
  2. 02

Mobilising a site?

Send your crane list and lift plan, or the families and capacities you need. We will quote a matched, certified rigging kit from stock.

Plant-down? Call +971 52 2477942 — 24/7

Keep reading

More on Lifting & rigging

All articles in this topic

Stainless steel lifting chain: Grade 60 ratings, where it is worth it, and its limits

3 min read

Beam trolleys: push or geared, and how to size one to the beam

3 min read

Back to Blog