Skip to content
+971 52 2477942
Lifting & rigging

Rigging for plant shutdowns and turnarounds: lifting points, chain blocks and certified kit

A shutdown compresses months of maintenance into weeks, and much of it is lifting: pump motors out, exchanger bundles pulled, valves swapped, in congested units with no room for a crane. The rigging that makes it possible — lifting points, chain blocks, lever hoists, beam clamps and trolleys — how to plan and certify it before the unit comes down, and how to keep the register straight when hundreds of items come and go.

Written by
Ayush Bhatia, Director
Published
Reading
3 min · 3 sections
Share

At a glance

Key takeaways

  1. Plan the lifts in the pre-shutdown scope: every motor, bundle and valve that comes out needs a lifting point, a lifting device and a route.
  2. Inside units, chain blocks and lever hoists on beam clamps and trolleys do most of the work; check that the steel they hang from is rated for lifting.
  3. Every item arrives marked, certified and registered before the unit comes down — not during the shutdown.
  4. Heavy or awkward lifts in congested plant are often critical lifts: plan them in writing.
  5. Control rigging in and out of the unit with the register, so nothing is left in the plant and nothing uncertified goes in.

Figures verified · OSHA 29 CFR 1926.251 marking and proof-test rules; lift planning per ASME P30.1 as described in industry sources; Abu Dhabi lifting code intervals. Your operator’s procedures govern.

Gas plants and refineries in the Gulf run for years between turnarounds, then stop for a few intense weeks of maintenance. A large part of that work is lifting in tight spaces: pump motors and couplings out of pump houses, exchanger bundles pulled, control valves and relief valves swapped, compressor parts lifted from casings — usually under pipe racks and between vessels where no crane can reach. Contractors who get the rigging planned, certified and staged before the unit comes down keep to the schedule. Those who source it during the shutdown do not.

/01Plan lifts in the scope.

  • List every item that will be lifted, with weight, lifting points and route out.
  • Identify fixed lifting points — runway beams, pad eyes, monorails — and confirm they are rated and in date.
  • Where there is no fixed point, design one: a beam clamp on a rated beam, or a temporary frame, approved by an engineer.
  • Classify the lifts: routine, or critical — near capacity, over live plant, in congested areas, or with multiple hoists. Lift-planning practice such as ASME P30.1 calls for a more detailed written plan for critical lifts.
  • From the list, build the rigging schedule: hoists, clamps, trolleys, slings, shackles, quantities and capacities.

/02The in-unit kit.

Shutdown hoisting kit
ItemRole
Manual chain blocksVertical lifting from a fixed point; fine control
Lever hoistsHighlightedPulling, tensioning and positioning at any angle
Beam clampsTemporary hanging point on a rated beam flange
Push and geared beam trolleysTravel along a runway beam with the load
Lifting points and swivelsRated attachment to equipment
Slings and shacklesConnecting hoist to load

Our range covers chain blocks from 0.5 t to 30 t and more, lever hoists, beam clamps, geared and push beam trolleys and close-headroom trolley hoists for low beams. Match trolley to beam flange width and hoist capacity. See chain block vs lever hoist vs electric hoist.

/03Certified before the unit comes down.

Every item that goes into the unit should arrive marked with its rated load, with its certificate, and be entered in the shutdown lifting register before day one. In the US, OSHA requires rigging to carry its safe working load marking, and custom lifting accessories such as clamps to be marked and proof-tested to 125% of rated load before use. In Abu Dhabi, lifting accessories are examined every 6 months by approved third parties; a shutdown is a bad moment to discover an item’s certificate has lapsed. See what a lifting gear test certificate should show.

Common questions

Chain block or lever hoist for shutdown work?
Chain blocks for vertical lifts from a fixed point; lever hoists for pulling, tensioning and positioning at any angle. Most shutdowns need both.
Can I hang a chain block from any beam?
Only from a beam rated and approved for lifting. Use a beam clamp or trolley matched to its flange.
What is a critical lift in a shutdown?
A lift near capacity, over live plant, in congested areas or with multiple hoists. Plan it in writing.
When should shutdown rigging be certified?
Before the shutdown starts — marked, certified and registered before it goes into the unit.
Can you supply a shutdown rigging package?
Yes. Send the rigging schedule and dates and we will quote certified chain blocks, hoists, clamps, trolleys, slings and shackles.

Shutdown hoisting kit

IndustryOil and gasCertified rigging for plant and shutdown work.

What next

  1. 01
  2. 02

Planning a turnaround?

Send the rigging schedule and shutdown dates. We will quote certified hoisting kit, delivered and documented before the unit comes down.

Plant-down? Call +971 52 2477942 — 24/7

Keep reading

More on Lifting & rigging

All articles in this topic

Stainless steel lifting chain: Grade 60 ratings, where it is worth it, and its limits

3 min read

Beam trolleys: push or geared, and how to size one to the beam

3 min read

Back to Blog